PMI Formulas

This is a very basic study aid for typing and memorizing the PMI’s Project Management formulas. The answers are available by scrolling down to a completed table below. You can use the first table to test yourself.

As recommended by Rita, I generally tried to express each formula description at least once in my own words. I find it helps me initially to understand them and later to recall them, but this does leave room for variance in interpretation. Feel free to advise me of any corrections, clarity needed, or suggestions.

Acronym Name or Formula Interpretation
EAD
Activity Standard Deviation
Activity Variance
EV
PV
AC
BAC
CV
SV
CPI
SPI
EAC
ETC
VAC
TCPI
AWCS
EAD
AV
SD
Activity Range
Project Expected Duration
Project SD
Project Range
EMV
Communication Channels
PTA
Final Fee
Final Price
Float
Formula
Formula
Formula
Formula

1x100_transparent_box

1x100_transparent_box

1x100_transparent_box

Notes:

  1. Except for TCPI, the 4 letter formula acronyms are either dated or invalid.
  2. EV comes first
  3. Actual cost must be provided in the question
  4. “Not enough information is provided.” is a possible correct answer
  5. Variance formulas are EV – something
  6. Index formulas are EV / something
  7. Cost formulas use CV
  8. Schedule formulas use PV
  9. For variance, negative is bad. Positive is good.
  10. For indices, > 1 is good. < 1 is bad.
Acronym Name or Formula Interpretation
EV Earned Value The estimated value of the work completed.
The completed portion of the originally estimated, total value.
PV Planned Value The value of the work planned to be be done by now
AC Actual Cost The current amount spent.
The total cost so far for the work completed.
BAC Budget At Completion The total project budget
How much did we originally expect the total project to cost?
BAC = PV of entire project
CV Cost Variance
EV – AC
Value of work accomplished – cost incurred
SV Schedule Variance
EV – PV
The value of work completed – The value of work planned to be completed.
Work completed – Expected work completed
Negative is behind schedule. Positive is ahead of schedule.
CPI Cost Performance Index
EV / AC
We are getting X value out of each $ spent.
Also as: “Cumulative CPI” when figures used are costs to date.
SPI Schedule Performance Index
EV / PV
We are progressing at X rate originally planned.
We are getting X value per original planned value.
EAC Estimate At Completion

AC + Bottom-up ETC



BAC / CPI



AC + (BAC – EV)




AC + [ (BAC - EV) / ( CPI + SPI) ]

What we currently expect the total cost to be.

Current cost + Bottom up (redone) estimate of remaining cost. Used when original estimate was flawed.

Currently, the total cost estimate per (cumulative) performance.
Used when there is no variance from BAC. Most common on exam.

Current cost + Remaining work TBD.
What you’ve spent + What you need to spend.
Used when current variance is expected to change.

Current cost plus remaining budget per performance.
Used when variance is typical, CPI is poor, and completion date priority is high

TCPI To Complete Performance Index
(BAC – EV) / (BAC – AC)
The remaining work TBD per the remaining money.
In order to stay on budget, what remaining performance is needed?
ETC Estimate To Complete
EAC – AC


Reestimate
How much more will the project cost?
Updated total cost – current cost


Reestimating the work from the bottom up.
VAC Variance At Completion
BAC – EAC
How much over/under budget will we be?
AWCS Actual Cost of Work Scheduled Not a real term!
Oxymoron
May be an incorrect test question choice.
EAD Expected Activity Duration

( P + 4M + O ) / 6

The most likely estimated is weighed 4 times the pessimistic or optimistic.This and all formulas below can be used for activity time and cost
AV Activity Variance

[ ( P - O ) / 6 ] ^2

A quantifiable deviation from an expected baseline or estimate. Also equal to standard deviation squared.
SD Standard Deviation

( P – O ) / 6

The square root of the variance. Used to calculate the activity range. EAD +/- SD
Activity Range EAD +/- SD The estimated scope from EAD – Standard Deviation to EAD + Standard Deviation.
Project Expected Duration EAD + EAD + EAD The sum of the EAD’s / PERT estimates
Project SD Standard deviation of the project

sqrt[AV + AV + AV ...]

Each of the activity variances (AV) on the critical path are calculated individually. The square root of their sum is the project standard deviation. It is used to calculate the project range.
Project Range The project expected duration +/- Project SD The sum of the project EADs +/- the project standard deviation.
EMV Expected Monetary Value

EMV = P * I

EMV = Probability times Impact
Communication Channels [ n (n-1) ] / 2 The number of channels between people. n is the number of people
PTA [(CP - TP) / BSR] + TC Point of total assumption.
The amount at which seller pays all additional costs. Used in FPIF contracts.
The margin between the maximum and target prices is divided by the buyer’s portion of the sharing ratio and added to the target cost
Final Fee FF = (TC – AC) x SSR + TF Sellers fee/profit is adjusted for cost performance.
The target fee is adjusted by adding: target cost – actual cost times the sellers portion of the sharing ratio
Final Price FP = AC + FF (or CP, whichever is lower) Final price equals actual cost plus final fee (or ceiling price)
Buy or Lease Purchase CostOwning Cost * Time = Leasing Cost * Time So if something costs $1,000 to buy and $10 / day to maintain but costs $50 / day to rent, how many days does it take to break even?  1,000 + 10 * t = 50 * t The break even point is 25 days.
Float Float = LF – LS or LS – ES Late Finish – Early Finish or Late Start – Early Start

Leave a Reply

 

 

 

(required)

Subscribe without commenting