PMI ITTOs
The inputs, tools and techniques, and outputs of the 42 PMI processes.
Misc Study Notes:
- The inputs and outputs are often artifacts of the project such as documents where the tools and techniques are often methods, like brainstorming.
- The inputs to processes are often the outputs of previous processes.
- Since the enterprise environmental factors and organizational process assets are generally different for each process, these are abbreviated and then detailed in each occurrence.
- To help derive (vs. memorize) EFFs, answer the question, “What intangibles will influence this process?” Examples: culture, marketplace, and industry standards.
- To help derive (vs. memorize) OPAs, answer the question, “What resources can assist this process?” Examples: templates, same documents from previous projects, and lessons learned database.
- I’ve drafted writing templates for learning and self-testing the ITTOs. It indicates the number of each items needed for each ITTO of all the 42 processes as a hint while learning and writing them. They are arranged by knowledge area, since that is how most people learn them. The PDF is available here. a previous breakout by process flow is here. A still older version is here.
Use the first table to practice writing in the ITTOs of any PMI process. Scroll down for the completed ITTO tables.



| Develop Project Charter |
| Input |
Tools & Techniques |
Output |
| Project statement of work |
Expert judgment |
Project charter |
| Business case |
|
|
| Contract (if third party project) |
|
|
| EEF: government/industry standards, organizational infrastructure, marketplace conditions |
|
|
| OPA: Org’s standard processes, policies, definitions, templates, historical info and lessons learned |
|
|
Identify Stakeholders
|
| Input |
Tools & Techniques |
Output |
| Project Charter |
Stakeholder analysis |
Stakeholder register |
| Procurement Documents |
Expert judgment |
Stakeholder management strategy |
| EEF: Company Culture, structure, government and industry standards |
|
|
| OPA: Stakeholder register templates, previous stakeholder registers, lessons learned |
|
|
| Develop Project Management Plan |
| Input |
Tools & Techniques |
Output |
| Project charter |
Expert judgment |
Project management plan |
| Planning process outputs |
|
|
| EEF: Government/industry standards, org structure/infrastructure/culture, project management system |
|
|
| OPA: Standardized guidelines, proposal/performance eval criteria, PMP templates, closure templates, change control procedures, previous project docs like calendars, registers, and baselines. |
|
|
| Collect Requirements |
| Input |
Tools & Techniques |
Output |
| Project charter |
Interviews |
Requirements documentation |
| Stakeholder register |
Focus groups |
Requirements management plan |
|
Facilitated workshops |
Requirements traceability matrix |
|
Group creativity techniques: brainstorming, nominal group technique, Delphi technique, idea/mind mapping, affinity diagram. |
|
|
Group decision making techniques: unanimity, majority, plurality, dictatorship |
|
|
Questionnaires and surveys |
|
|
Observations |
|
|
Prototypes |
|
|
|
|
| Define Scope |
| Input |
Tools & Techniques |
Output |
| Project charter |
Expert judgment |
Project scope statement |
| Requirements documentation |
Product analysis |
Project document updates |
| OPA: Scope statement policies, procedures and templates. Previous project files and lessons learned. |
Alternatives identification |
|
|
Facilitated workshops |
|
| Create WBS |
| Input |
Tools & Techniques |
Output |
| Project scope statement |
Decomposition |
WBS |
| Requirements documentation |
|
WBS dictionary |
| OPA: WBS policies, procedures, and templates. Previous project files, lessons learned |
|
Scope baseline |
|
|
Project document updates |
| Define Activities |
| Input |
Tools & Techniques |
Output |
| Scope baseline (WBS, WBS dictionary, and Project Scope Statement) |
Decomposition |
Activity list |
| EEF: PMIS (project management information system) |
Rolling wave planning |
Activity attributes |
| OPA: activity planning related policies, procedures, guidelines. e.g. the scheduling methodology. |
Templates |
Milestone list |
|
Expert judgment |
|
Sequence Activities
|
| Input |
Tools & Techniques |
Output |
| Activity list |
Dependency determination |
Project schedule network diagrams |
| Activity attributes |
Precedence diagramming method (PDM) |
Project document updates |
| Milestone list |
Applying leads and lags |
|
| Project scope statement |
Schedule network templates |
|
| OPA: e.g. scheduling methodology files, previous project network diagrams |
|
|
Estimate Activity Resources
|
| Input |
Tools & Techniques |
Output |
| Activity list |
Expert judgment |
Activity resource requirements |
| Activity attributes |
Alternatives analysis |
Resource breakdown structure |
| Resource calendars |
Published estimating data |
Project document updates |
| EEF: e.g. resource availability and skills |
Bottom-up estimating |
|
| OPA: Policies and procedures for staffing, renting and purchasing, historical resource usage information |
Project management software |
|
Estimate Activity Durations
|
| Input |
Tools & Techniques |
Output |
| Activity list |
Expert judgment |
Activity duration estimates |
| Activity attributes |
Analogous estimating (top down) |
Project document updates |
| Activity resource requirements |
Parametric estimating (plotted forecasts) |
|
| Resource calendars |
Three-point estimating (PERT) |
|
| Project scope statement |
Reserve analysis |
|
| EEF: Reference data, e.g. duration estimating databases, productivity metrics, published commercial information |
|
|
| OPA: historical duration information, project calendars, scheduling methodology and lessons learned. |
|
|
Develop Schedule
|
| Input |
Tools & Techniques |
Output |
| Activity list |
Schedule network analysis |
Project schedule |
| Activity attributes |
Critical path method |
Schedule baseline |
| Project schedule network diagram |
Critical chain method |
Schedule data |
| Activity resource requirements |
Resource leveling |
Project document updates |
| Activity duration estimates |
Scheduling tool |
|
| Resource calendars |
What-if scenario analysis |
|
| Project scope statement |
Applying leads and lags |
|
| EEF: e.g., a company’s scheduling tool |
Schedule compression |
|
| OPA: Scheduling methodology and project calendar |
|
|
Estimate Costs
|
| Input |
Tools & Techniques |
Output |
| Scope baseline |
Expert judgment |
Activity cost estimates |
| Project schedule |
Analogous estimating |
Basis of estimates |
| Human resource plan |
Parametric estimating |
Project document updates |
| Risk register |
Bottom-up estimating |
|
| EEF: Market conditions, published commercial information |
Three-point estimates |
|
| OPA: cost estimating policies and templates, historical information and lessons learned |
Reserve analysis |
|
|
Cost of quality |
|
|
Project management estimating software |
|
|
Vendor bid analysis |
|
Determine Budget
|
| Input |
Tools & Techniques |
Output |
| Activity cost estimates |
Cost aggregation |
Cost performance baseline |
| Basis of estimates |
Reserve analysis |
Project funding requirements |
| Scope baseline |
Expert judgment |
Project document updates |
| Project schedule |
Historical relationships |
|
| Resource calendars |
Funding limit reconciliation |
|
| Contracts |
|
|
| OPA: cost budgeting related policies, procedures, and guidelines. Cost budgeting tools, reporting methods |
|
|
Plan Quality
|
| Input |
Tools & Techniques |
Output |
| Scope baseline |
Cost-benefit analysis |
Quality management plan |
| Stakeholder register |
Cost of quality |
Quality metrics |
| Cost performance baseline |
Control charts |
Quality checklists |
| Schedule baseline |
Benchmarking |
Process improvement plan |
| Risk register |
Design of experiments |
Project document updates |
| EEF: Associated rules, standards, and guidelines. Government agency regulations. Product’s working / operating conditions. |
Statistical sampling |
|
| OPA: Organizational quality policies, procedures, and guidelines, historical databases, lessons learned, quality policy (either an endorsed as-is policy or one created by the PM and communicated to stakeholders.) |
Flowcharting |
|
|
Proprietary quality management methodologies (e.g. Six Sigma) |
|
|
Additional quality planning tools (Group decision techniques, matrices, ..) |
|
Develop Human Resources Plan
|
| Input |
Tools & Techniques |
Output |
| Activity resource requirements |
Org charts and position descriptions |
Human resources plan: roles and responsibilities, org charts and staffing management plan: resource calendars, acquisition and release, recognition and rewards, safety, compliance and training. |
| EEF: Company culture, organization, HR, personnel policies, market |
Networking |
|
| OPA: org chart templates, historical project org info, standard processes and roles descriptions |
Organizational theory |
|
Plan Communications
|
| Input |
Tools & Techniques |
Output |
| Stakeholder register |
Communication requirements analysis |
Communications management plan |
| Stakeholder management strategy |
Communication technology |
Project document updates |
| EEF: All the other EEF are used here |
Communication models: components are encoding, message/feedback, medium, noise, and decoding |
|
| OPA: Lessons learned and historical info from previous projects, as well as all other OPAs. |
Communication methods: push, pull and interactive |
|
Plan Risk Management
|
| Input |
Tools & Techniques |
Output |
| Project scope statement |
Planning meetings and analysis |
Risk management plan |
| Cost management plan |
|
|
| Schedule management plan |
|
|
| Communications management plan |
|
|
| EEF: risk attitudes and tolerances |
|
|
| OPA: stakeholder registers, risk categories, common definitions, templates |
|
|
Identify Risks
|
| Input |
Tools & Techniques |
Output |
| Risk management plan |
Documentation reviews |
Risk register |
| Activity cost estimates |
Information gathering techniques |
|
| Activity duration estimates |
Checklist analysis |
|
| Scope baseline |
Assumptions analysis |
|
| Stakeholder register |
Diagramming techniques |
|
| Cost management plan |
SWOT analysis |
|
| Schedule management plan |
Expert judgment |
|
| Quality management plan |
|
|
| Project documents |
|
|
| EEF: Risk attitudes, benchmarking, and published information: checklists, databases, studies. |
|
|
| OPA: Project files, process controls, risk statement templates, lessons learned. |
|
|
Perform Qualitative Risk Analysis
|
| Input |
Tools & Techniques |
Output |
| Risk register |
Risk probability and impact assessment |
Risk resister updates:
Risk category grouping
Project risk ranking
Watchlist
Probability estimates of project objectives
Trends of the above data during the project |
| Risk management plan |
Probability and impact matrix |
|
| Project scope statement |
Risk data quality assessment |
|
| OPA: similar project info and project studies, industry risk databases |
Risk categorization |
|
|
Risk urgency assessment |
|
|
Expert Judgment |
|
Perform Quantitative Risk Analysis
|
| Input |
Tools & Techniques |
Output |
| Risk register |
Data gathering and representation techniques: interviewing, probability distributions |
Risk resister updates:
List of prioritized, quantified risks
Contingency time and cost reserves
Project estimates: Time and Date vs. Confidence
Probability estimates of project objectives
Trends of the above data during the project |
| Risk management plan |
Quantitative risk analysis and modeling techniques: sensitivity analysis, EMV analysis/decision tree, modeling and simulation (e.g. monte carlo) |
|
| Cost management plan |
Expert judgment |
|
| Schedule management plan |
|
|
| OPA: similar project info and project studies, industry risk databases |
|
|
Plan Risk Responses
|
| Input |
Tools & Techniques |
Output |
| Risk register |
Strategies for negative risks or threats |
Risk resister updates:
Residual risks
Secondary risks
Contingency plans
Risk response owners
Fallback plans
Risk triggers
Contracts
Reserves |
| Risk management plan |
Strategies for positive risks or opportunities |
Risk-related contract decisions |
|
Contingent response strategies |
Project management plan updates |
|
|
Project document updates |
Plan Procurements
|
| Input |
Tools & Techniques |
Output |
| Scope baseline |
Make-or-buy analysis |
Procurement management plan |
| Requirements documentation |
Expert judgment |
Procurement statements of work |
| Teaming aggreements |
Contract types |
Make-or-buy decisions |
| Risk register |
|
Procurement documents |
| Risk-related contract decisions |
|
Source selection criteria |
| Activity resource requirements |
|
Change requests |
| Project schedule |
|
|
| Activity cost estimates |
|
|
| Cost performance baseline |
|
|
| EEF: market, availability, suppliers, locale, industry T&Cs |
|
|
| OPA: purchasing policies, management systems, supplier system |
|
|
| Direct And Manage Project Execution |
| Input |
Tools & Techniques |
Output |
| Project management plan |
Expert judgment |
Deliverables |
| Approved change requests |
Project management information system |
Work performance information |
| EEF: Infrastructure, personnel rules, stakeholder risk tolerances, project management information systems |
|
Change requests |
| OPA: Standardized work guidelines, communication requirements, defect management procedures, project files from previous projects |
|
Project management plan updates |
|
|
Project document updates |
Perform Quality Assurance
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Plan Quality and Perform Quality Control tools and techniques |
OPA updates |
| Quality metrics |
Quality audits |
Change requests |
| Work performance information |
Process analysis |
Project management plan updates |
| Quality control measurements |
|
Project document updates |
Acquire Project Team
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Pre-assignment |
Project staff assignments |
| EEF: Org’s skill levels and structure, personnel policies, locale, |
Negotiation |
Resource calendars |
| OPA: Org’s standard policies, processes, and procedures |
Acquisition |
Project management plan updates |
|
Virtual teams |
|
| Develop Project Team |
| Input |
Tools & Techniques |
Output |
| Project staff assignments |
Interpersonal skills |
Team performance assessments |
| Project management plan |
Training |
EEF updates |
| Resource calendars |
Team-building activities |
|
|
Ground rules |
|
|
Co-location |
|
|
Recognition and rewards |
|
Manage Project Team
|
| Input |
Tools & Techniques |
Output |
| Project staff assignments |
Observations and conversation |
EEF updates |
| Project management plan |
Project performance appraisals |
OPA updates |
| Team performance assessments |
Conflict management |
Change requests |
| Performance reports |
Issue log |
Project management plan updates |
| OPA: bonus structures, certificates of appreciation, newsletters, perks |
Interpersonal skills |
|
Distribute Information
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Communication methods: mostly push method, like email, memos, etc, but include meetings, teleconferences, online chat, etc. |
OPA updates |
| Performance reports |
Information distribution tools |
|
| OPA: information distribution guidelines and policies, lessons learned and historical project information |
|
|
Manage Stakeholder Expectations
|
| Input |
Tools & Techniques |
Output |
| Stakeholder register |
Communication methods |
OPA updates |
| Stakeholder management strategy |
Interpersonal skills |
Change requests |
| Project management plan |
Management skills |
Project management plan updates |
| Issue log |
|
Project document updates |
| Change log |
|
|
| OPA: org communication requirements, change control and issue management procedures |
|
|
Conduct Procurements
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Bidder conferences |
Selected sellers |
| Procurement documents |
Proposal evaluation techniques |
Procurement contract awards |
| Source selection criteria |
Independent estimates |
Resource calendars |
| Qualified seller list |
Expert judgment |
Change requests |
| Seller proposals |
Advertising |
Project management plan updates |
| Project documents |
Internet search |
Project document updates |
| Make-or-buy decisions |
Procurement negotiations |
|
| Teaming aggreements |
|
|
| OPA: prospective/qualified seller lists, historical seller information |
|
|
Monitor and Control Project Work
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Expert judgment |
Change requests |
| Performance reports |
|
Project management plan updates |
| EEF: Industry/Gov standards, stakeholder risk tolerances, project management information systems |
|
Project document updates |
| OPA: org communications requirements, financial controls procedures, defect management procedures, risk control/categories/matrices |
|
|
Perform Integrated Change Control
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Expert judgment |
Change request status updates (approved change requests and denied change requests) |
| Work performance information |
Change control meetings |
Project management plan updates |
| Change requests |
|
Project document updates |
| EEF: project management information system such as a scheduling tool |
|
|
| OPA: change control procedures, process measurement database, project files like baselines, configuration management databases |
|
|
Verify Scope
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Inspection |
Accepted deliverables |
| Requirements documentation |
|
Change requests |
| Requirements traceability matrix |
|
Project document updates |
| Validated deliverables |
|
|
Control Scope
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Variance analysis |
Work performance measurements |
| Work performance information |
|
OPA updates |
| Requirements documentation |
|
Change requests |
| Requirements traceability matrix |
|
Project management plan updates |
| OPA: scope related policies, guidelines, procedures. Monitoring and reporting methods to be used. |
|
Project document updates |
Control Schedule
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Performance reviews |
Work performance measurements |
| Project schedule |
Variance analysis |
OPA updates |
| Work performance information |
Project management software |
Change requests |
| OPA: Schedule control tools, related policies, guidelines, procedures. Monitoring and reporting methods to be used. |
Resource leveling |
Project management plan updates |
|
What-if scenario analysis |
Project document updates |
|
Adjusting leads and lags |
|
|
Schedule compression |
|
|
Scheduling tool |
|
Control Costs
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Earned value management |
Work performance measurements |
| Project funding requirements |
Forecasting |
Budget forecasts |
| Work performance information |
To-Complete Performance Index (TCPI) |
Organization process assets updates |
| OPA: cost control-related policies procedures and guidelines. Cost control tools and monitoring / reporting methods to be used. |
Performance reviews |
Change requests |
|
Variance analysis |
Project management plan updates |
|
Project management software |
Project document updates |
Perform Quality Control
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Cause and effect diagrams |
Quality control measurements |
| Quality metrics |
Control charts |
Validated changes |
| Quality checklists |
Flowcharting |
Validated deliverables |
| Work performance measurements |
Histogram |
OPA updates |
| Approved change requests |
Pareto chart |
Change requests |
| Deliverables |
Run chart |
Project management plan updates |
| OPA: quality standards and policies, standard work guidelines, and issue / defect reporting procedures |
Scatter diagram |
Project document updates |
|
Statistical sampling |
|
|
Inspection |
|
|
Approved change requests review |
|
Report Performance
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Variance analysis |
Performance reports |
| Work performance information |
Forecasting methods |
OPA updates |
| Work performance measurements |
Communication methods |
Change requests |
| Budget forecasts |
Reporting systems |
|
| OPA: report templates, measurement indicator definitions, organization’s variance limits |
|
|
Monitor And Control Risks
|
| Input |
Tools & Techniques |
Output |
| Risk register |
Risk reassessment |
Risk register updates |
| Project management plan |
Risk audits |
OPA updates: technical documentation and assumptions |
| Work performance information |
Variance and trend analysis |
Change requests |
| Performance reports |
Technical performance measurement |
Project management plan updates |
|
Reserve analysis |
Project document updates |
|
Status meetings |
|
| Administer Procurements |
| Input |
Tools & Techniques |
Output |
| Procurement documents |
Contract change control system |
Procurement documentation |
| Project management plan |
Procurement performance reviews |
OPA updates |
| Contract |
Inspections and audits |
Change requests |
| Performance reports |
Performance reporting |
Project management plan updates |
| Approved change requests |
Payment systems |
|
| Work performance information |
Claims administration |
|
|
Records management system |
|
Close Procurements
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Procurement audits |
Closed procurements |
| Procurement documentation |
Negotiated settlements |
OPA Updates |
|
Records management system |
|
Close Phase Or Project
|
| Input |
Tools & Techniques |
Output |
| Project management plan |
Expert judgment |
Final product, service, or result transition |
| Accepted deliverables |
|
OPA updates |
| OPA: closure guidelines, audits, evaluations and other project docs |
|
|
|
|
Great information, Much appreciated for all your hard work with future PM community…
This great. I am in the process of studying for the PMP exam and the ITTO charts are one of my weaknesses. This will help me alot. Thanks for sharing.
Hey thanks folks! The feedback is appreciated.
Best,
Mark
Hey Mark,
Fabulous job. One quick question if you know the answer of the top of your head. Why did PMBOK editors remove ‘Cost Management Plan’from “DETERMINE BUDGET” process. Wondering coz it was there in the 3rd edition and make sense as cost processes as governed by the Cost management plan. Was it replaced by something or made redundant?
Would like to hear your view.
regards
Fawzia (Pakistan)
Hello Fawzia,
Great question and great to hear from Pakistan!
I think sometimes PMBOK changes how they categorize. The Cost Management Plan is no longer an explicit output of any process but is an input of several. So I expect it is how you suggest, that the outputs of Determine Budget include the Cost Performance Baseline which feeds into the Project Management Plan. So it looks like the Cost Performance Plan is not created as an output of a single process.
This is similar to how the Scope Baseline is not a single output, but then is used as an input when its components (WBS, WBS dictionary, and Project Scope Statement) have each been output.
I hope this helps!
Best,
Mark
Thanks Mark. Your reply makes sense. Appreciate your quick response.
Regards,
Fawzia
Hello Mark,
May I also suggest a new tool for practicing ITTOs for the PMP / CAPM exams? It has an ITTO Quiz, an ITTO explorer and also gives detailed graphical analytics. Here’s the link:
http://www.brainbok.com
I’ll appreciate feedback from you and your readers.
Thanks.
[...] ITTOs http://markpreynolds.com/pmp/ittos [...]
[...] ITTOs http://markpreynolds.com/pmp/ittos [...]
really the information are very much helpful
[...] ITTOs http://markpreynolds.com/pmp/ittos [...]
[...] you can see others ITTOs’ memorizing strategies (the X strategy, the Y strategy, and the Z strategy). I used my-one numerical mapping strategy to increase my confidence in some of these [...]
[...] pero trataba de repasarlo ambos cada vez que podía. La estructura original no es de mi autoría, la encontré en el Internet. Sin embargo, la edité para que fuera cómoda a la vista y accesible al tenerlas en pdf. El [...]